Indonesia Weda Bay Industrial Park (IWIP)

In IWIP, PT. CCEPC Indonesia has undertaken large-scale infrastructure development, including 17 power plant units with a total capacity of 5,680 MW, as well as desulfurization and denitrification systems. The scope also covers the construction of four 1-million-ton sulfuric acid production plants, roof-mounted distributed photovoltaic systems, and integrated water and wastewater collection and treatment facilities.

Energy

  • Tsingshan Power Generation Unit Construction Projects, Units No. 1–19:
    • 6 × 250 MW
    • 11 × 380 MW
    • 2 × 710 MW
  • Waste Heat Power Generation Project for Sulfuric Acid Production
  • Tsingshan Power Generation Unit Maintenance Project

Environmental Protection

  • Flue Gas Desulfurization and Denitrification Projects for Units No. 1–4 and No. 9–11
  • High-Grade Nickel Matte Desulfurization Project
  • Sintering Flue Gas Desulfurization Project
  • Industrial Park Stormwater Management Project

Diversified Business

  • Chemical Engineering: 4 × 1 Million-Ton Sulfuric Acid Production Projects
  • Hydrometallurgy / Chemical Engineering: Supporting Installation Project for Huaxiang Nickel Sulfate
  • Civil Construction: Tsingshan Building Project, approximately 98 meters high, with a total floor area of approximately 50,000 m²
  • Solar Power Generation: Distributed Solar PV Project for Supporting Facilities of Power Plant Units No. 1–8
  • Other Projects:
    • Nickel Electrolysis Installation and Civil Engineering Project
    • Sakai River Expansion Project
    • Non-Destructive Testing Project for Jiaman New Energy Company
    • Design Project for J-Line and R-Line of the Hydrometallurgy Integrated Pipeline Network and Pipe Rack